Which SMRs are actually being built
Every design here is ranked by what a regulator has actually done, not by what the developer has announced. Of 26 tracked designs, 12 have a construction permit or better and 2 are generating power. The rest are under review or have not yet filed an application at all.
12 of 26 designs need HALEU, uranium enriched above 5%. Western production currently runs at roughly 900 kilograms a year from a single demonstration cascade, against a US need the Department of Energy puts at 50 tonnes a year by 2035 (below). 4 of the 12 designs already permitted or building are in that queue. A reactor can be licensed, financed and built and still have nothing to run on.
Some of these are small enough to travel on a truck, microreactors that ship in containers are covered separately.
Where the designs stand
The designs tracked here add up to 3,577 MWe, of which 1,507 MWe, 42%, belongs to designs with a permit or further along. Most of the pipeline is still at the stages where nothing has been approved.
Each block is a design; amber blocks need HALEU. Output is electrical where the design states one; a few research and test reactors give only a thermal rating and add nothing to the MWe totals.
Where the first units would go
20 designs name a first site, in 6 countries: United States9, Russia4, China2, Canada2, United Kingdom2 and Argentina1. 6 (NuScale US460 (VOYGR), eVinci, IMSR (Integral Molten Salt Reactor), BANR, SMART, Nuward) name none. Idaho National Laboratory hosts several, because a Department of Energy site lets a demonstration reactor proceed under DOE authorisation rather than a commercial licence.
Every design
| Design | Developer | Regulatory position | MWe | Fuel | Regulator | Units announced |
|---|---|---|---|---|---|---|
| HTR-PM | China National Nuclear Corporation | 210 | LEU | National Nuclear Safety Administration (China) | 3 | |
| KLT-40S (Akademik Lomonosov) | Rosatom | 35 | LEU | Rostechnadzor (Russia) | 2 | |
| BWRX-300 | GE Vernova Hitachi Nuclear Energy | Under construction | 300 | LEU | CNSC (Canada) and US NRC | 47 |
| BREST-OD-300 | Rosatom | Under construction | 300 | LEU | Rostechnadzor (Russia) | 1 |
| ACP100 (Linglong One) | China National Nuclear Corporation | Under construction | 125 | LEU | National Nuclear Safety Administration (China) | 7 |
| RITM-200S | Rosatom | Under construction | 106 | LEU | Rostechnadzor (Russia) | 8 |
| RITM-200N | Rosatom | Under construction | 55 | LEU | Rostechnadzor (Russia) | 6 |
| CAREM-25 | Comisión Nacional de Energía Atómica | Under construction | 29 | LEU | Autoridad Regulatoria Nuclear (Argentina) | 1 |
| Project Pele | BWX Technologies | Under construction | 2 | HALEU | US Department of Defense / Department of Energy authorisation | - |
| Hermes | Kairos Power | Under construction | 35 MWt | HALEU | US NRC | 5 |
| Natrium | TerraPower | Permitted | 345 | HALEU | US NRC | - |
| Hermes 2 | Kairos Power | Permitted | 70 MWt | HALEU | US NRC | - |
| SMART | Korea Atomic Energy Research Institute | Design approved | 100 | LEU | Nuclear Safety and Security Commission (South Korea) | - |
| NuScale US460 (VOYGR) | NuScale Power | Design approved | 77 | LEU | US NRC | 61 |
| Rolls-Royce SMR | - | Under review | 470 | LEU | UK ONR and Environment Agency | - |
| SMR-300 | Holtec International | Under review | 300 | LEU | US NRC and UK ONR | 10 |
| Xe-100 | X-energy | Under review | 80 | HALEU | US NRC | 16 |
| Aurora | Oklo Inc. | Under review | 15 | HALEU | US NRC | - |
| Nuward | Électricité de France | Pre-application | 400 | LEU | ASNR (France), with a joint review by six European regulators | - |
| AP300 | Westinghouse Electric Company | Pre-application | 300 | LEU | UK ONR and Environment Agency, and US NRC | 4 |
| IMSR (Integral Molten Salt Reactor) | - | Pre-application | 195 | HALEU | US NRC and CNSC (Canada) | - |
| ARC-100 | - | Pre-application | 100 | HALEU | CNSC (Canada) | - |
| BANR | BWX Technologies | Pre-application | 17 | HALEU | US NRC | 8 |
| Aalo-1 | - | Pre-application | 10 | HALEU | US Department of Energy authorisation pathway | 12 |
| eVinci | Westinghouse Electric Company | Pre-application | 5 | HALEU | US NRC | - |
| Kaleidos | - | Pre-application | 1 | HALEU | US Department of Energy authorisation pathway | - |
"Units announced" counts entries in the Global Nuclear Power Tracker carrying this design's model name, at any status including announced and cancelled. A high number is a measure of promotion, not of progress, compare it against the regulatory position beside it.
HALEU: what the designs need against what exists
12 of the 26 SMR and advanced designs tracked here need HALEU, uranium enriched to between 5% and 20%. 4 of them already have a permit or are being built (Hermes, Natrium, Hermes 2, Project Pele). The one HALEU production line running, at American Centrifuge Plant, Piketon, made 900 kg in its latest year: 1.8% of the 50 tonnes a year the US Department of Energy has said domestic demand could reach by 2035. Its 2029 target of 12 tonnes a year would be 24% of it.
Finite stocks on record: Savannah River Site HEU downblending, about 3.1 tonnes in all; Idaho National Laboratory EBR-II downblending, size not published. The demand figure is the Department of Energy's December 2024 estimate (source) and covers the United States only; no developer here publishes how much HALEU its first core needs. See HALEU for every production line and plan.
Sources
- US Nuclear Regulatory Commission, advanced reactor licensing , Public domain · retrieved 2026-09-06
- UK Office for Nuclear Regulation. Generic Design Assessment
- Canadian Nuclear Safety Commission. Vendor Design Review
- Announced unit counts: Global Nuclear Power Tracker, Global Energy Monitor, August 2026 release , CC BY 4.0
How these sources are used, including the corrections applied on top of them and what is deliberately left blank · download the underlying data