Where nuclear waste will finally go

Ten repositories are operating worldwide and not one of them takes commercial spent fuel. Nine take low and intermediate level waste, which several countries have been burying for decades; the tenth takes transuranic waste from the American weapons programme. For the fuel itself, Finland's Onkalo is built and awaiting its operating licence, Sweden is under construction at Forsmark, Canada selected a site in 2024 after fifteen years of consent-based siting, and everyone else is somewhere between planning and paralysis.

Facilities listed
21
across 14 countries
Operating
10
5 under construction
Planned
3
3 closed or abandoned
Operating capacity
800,000
drums, where published

The engineering has not been the hard part. The Finnish and Swedish KBS-3 method seals fuel into copper canisters, surrounds them with bentonite clay that swells when wet, and places them in tunnels hundreds of metres down in rock that has been geologically stable for a billion years. It has been studied for four decades and no serious technical objection has survived.

What has failed is consent. Repository siting has collapsed politically in more countries than it has succeeded in. Yucca Mountain absorbed two decades and billions of dollars, was selected by an act of Congress rather than by a search, never received a single fuel assembly, and lost its funding in 2010. Germany spent thirty years on Gorleben before abandoning it and restarting the search from a blank map.

The programmes that worked did the opposite. Finland and Sweden spent decades building local agreement before they moved rock, and both host municipalities volunteered. Canada's process ran fifteen years and ended with a willing community and a willing First Nation. What those three have in common is not geology, which is unremarkable in each case, but that nobody was told where the waste was going.

Most waste is not spent fuel, and most of it already has somewhere to go. Drigg in Cumbria has been taking low level waste since 1959, Finland has been putting it underground since 1992, and Sweden's SFR sits fifty metres below the Baltic seabed. These places work, and they are routinely counted alongside spent fuel repositories in a way that makes the problem look closer to solved than it is. The Waste Isolation Pilot Plant in New Mexico is the only deep geological repository in the world receiving waste, and it takes transuranic waste from the weapons programme. It is proof the concept works, not proof the harder problem is finished.

Germany is the record of what failure costs. Asse II took 47,000 cubic metres of waste into a salt mine on the assumption that salt stays dry. Water entered, and the decision now is to retrieve all of it, at an estimated 4.7 billion euros merely to be ready to begin in 2033. Morsleben, 37,000 cubic metres, is being sealed with its contents in place, the opposite decision. Konrad, licensed in 2002, is still being built.

Why this stage is a chokepoint

The bottleneck is consent, not capacity, geology or money. There is no shortage of suitable rock: stable formations exist in almost every country with a nuclear programme. What is scarce is a community that will accept the material, and the programmes that found one spent between fifteen and forty years doing so. That is the timescale everything else in this stage runs on, and it is why a country that starts now is not opening a repository this half-century.

What each repository actually takes

There are 10 operating repositories in the world. 9 of them take low and intermediate level waste, one takes transuranic waste from the American weapons programme, and none takes commercial spent fuel or high level waste. That distinction does most of the work on this page. Burying waste that does not generate heat is a solved problem that several countries have been doing for decades; burying waste that does is a problem no country has finished solving, and the two are routinely reported as though they were the same activity.

Every repository on record

Facility Takes OperatorCountry Capacity Status
Wolsong LILW Disposal Center, Gyeongju Low and intermediate level Korea Radioactive Waste Agency South Korea 800,000drums operating
Konrad Low and intermediate level Bundesgesellschaft für Endlagerung Germany 303,000m³ construction
Yucca Mountain Spent fuel US Department of Energy United States 70,000tHM total closed
Asse II Low and intermediate level Bundesgesellschaft für Endlagerung Germany 47,000m³ closed
Morsleben (ERAM) Low and intermediate level Bundesgesellschaft für Endlagerung Germany 37,000m³ closed
Bátaapáti National Radioactive Waste Repository Low and intermediate level Public Limited Company for Radioactive Waste Management Hungary not disclosed operating
Beishan underground research laboratory High level China National Nuclear Corporation China not disclosed construction
Canadian deep geological repository Spent fuel Nuclear Waste Management Organization Canada not disclosed planned
Centre de l'Aube (CSA) Low and intermediate level Andra France not disclosed operating
Cigéo High level Andra France not disclosed planned
El Cabril Low and intermediate level ENRESA Spain not disclosed operating
Forsmark spent fuel repository (KBS-3) Spent fuel Svensk Kärnbränslehantering (SKB) Sweden not disclosed construction
Loviisa VLJ repository Low and intermediate level Fortum Finland not disclosed operating
Low Level Waste Repository, Drigg Low and intermediate level Nuclear Waste Services United Kingdom not disclosed operating
Nördlich Lägern Spent fuel Nagra Switzerland not disclosed planned
Olkiluoto VLJ repository Low and intermediate level Teollisuuden Voima Finland not disclosed operating
Onkalo Spent fuel Posiva Oy Finland not disclosed construction
Rokkasho LLW Disposal Center Low and intermediate level Japan Nuclear Fuel Limited Japan not disclosed operating
SFR, Forsmark Low and intermediate level Svensk Kärnbränslehantering (SKB) Sweden not disclosed operating
Waste Isolation Pilot Plant Transuranic US Department of Energy United States not disclosed operating
Yeniseisky underground research laboratory, Krasnoyarsk High level National Operator for Radioactive Waste Management Russia not disclosed construction