WEST

Operating tokamak France

WEST is a tokamak fusion device run by CEA in France. It is operating. Like every fusion device built so far, it has produced no net electricity.

What it has actually demonstrated

Held a plasma for 1,337 seconds, over 22 minutes, with 2.6 GJ of injected energy, the longest tokamak plasma anywhere. It is a fully tungsten-walled machine, which is the material ITER will use and the reason the result matters beyond the duration itself.

Built inside the vessel of the older Tore Supra at Cadarache, a few kilometres from the ITER site. Long pulses in a tungsten environment are exactly the problem ITER has to solve, and WEST exists to solve it first at smaller scale. Duration records are not energy records: WEST puts far more energy in than it gets out, as every device on this page does.

Project
OrganisationCEA
Approachtokamak
Confinementmagnetic
CountryFrance
StatusOperating
First plasma2016
Targets
Target datenone stated
Power targetnone stated
Energy gain targetnone stated
Net electricityNo. no fusion device has produced any

Other tokamak projects

ProjectStatus
ARC Planned
BEST Under construction
DIII-D Operating
EAST Operating
HL-3 Operating
ITER Under construction
JET (Joint European Torus) Closed
JT-60SA Operating
K-DEMO Planned
KSTAR Operating
SPARC Under construction
ST40 Operating
STEP Planned

Fusion needs tritium, and the world's civilian stock comes mostly from CANDU fission reactors. See the fusion overview.

WEST in context

14 of the 24 fusion projects on record use the tokamak approach: 7 operating, 3 under construction, 3 planned and 1 closed.

Its first plasma is dated 2016, 10 years ago: the 9th earliest of 15 projects on record with a first-plasma date.

MeasureWESTMedian of all projectsStanding
First plasma201620159 of 15 (earliest first)

Worked out from the entries on this site only, so a figure compares WEST with what is recorded here, not with everything that exists. An entry with no value for a measure is left out of that measure's ranking and median.

Sources

How these sources are used, including the corrections applied on top of them and what is deliberately left blank · download the underlying data

Try

Searches every page: 1,823 reactors, 592 plants, 158 fuel chain facilities, companies, designs, accidents and notes.