ITER

Under construction tokamak France
Power target
500MW
target, not achieved

ITER is a tokamak fusion device run by ITER Organization (35 nations) in France. It is under construction. Like every fusion device built so far, it has produced no net electricity.

What it has actually demonstrated

Under construction. By mid-2026 the six-module central solenoid stack was complete on site and five of the nine vacuum vessel sector modules were installed in the tokamak pit.

The largest scientific collaboration in history after the ISS, and the machine everything else is measured against. Its schedule was rebaselined in 2024: scientific operations now start in 2034, full magnetic energy in 2036, and deuterium-tritium operation in 2039 — against an original plan for first plasma in 2025. The delays are attributed to the pandemic, quality problems, and optimistic planning for a first-of-a-kind machine. ITER will not generate any electricity. It is designed to show that a burning plasma can be sustained, not to sell power.

Project
OrganisationITER Organization (35 nations)
Approachtokamak
Confinementmagnetic
CountryFrance
StatusUnder construction
First plasmanot yet
Targets
Target date2034
Power target500MW
Energy gain targetQ = 10 (500 MW of fusion power from 50 MW of heating)
Net electricityNo. no fusion device has produced any

Other tokamak projects

ProjectStatus
ARC Planned
EAST Operating
JET (Joint European Torus) Closed
JT-60SA Operating
K-DEMO Planned
KSTAR Operating
SPARC Under construction
ST40 Operating
STEP Planned

Fusion needs tritium, and the world's civilian stock comes mostly from CANDU fission reactors. See the fusion overview.

Sources