Skip to content

BEST

Under construction tokamak China
Power target
200MW
target, not achieved

BEST is a tokamak fusion device run by Institute of Plasma Physics, Chinese Academy of Sciences in China. It is under construction. Like every fusion device built so far, it has produced no net electricity.

What it has actually demonstrated

Nothing yet: civil works began in 2023 and first deuterium plasma is targeted for 2027. It is included because it is the most consequential fusion machine under construction after ITER and the only one whose stated purpose is to demonstrate electricity generation from a burning plasma. Designed for 20 to 200 MW of fusion power, with a 3.6 metre major radius and a plasma current of 4 to 7 MA. Deuterium-tritium operation is described as under review rather than committed.

If it works to schedule, China would demonstrate electricity from fusion before ITER produces its first plasma. Building it in four years, on a site adjacent to EAST, is a different approach from ITER's thirty-five-nation consortium, and the schedule is the claim most worth watching sceptically.

Project
OrganisationInstitute of Plasma Physics, Chinese Academy of Sciences
Approachtokamak
Confinementmagnetic
CountryChina
StatusUnder construction
First plasmanot yet
Targets
Target date2027
Power target200MW
Energy gain targetnone stated
Net electricityNo. no fusion device has produced any

Other tokamak projects

ProjectStatus
ARC Planned
DIII-D Operating
EAST Operating
HL-3 Operating
ITER Under construction
JET (Joint European Torus) Closed
JT-60SA Operating
K-DEMO Planned
KSTAR Operating
SPARC Under construction
ST40 Operating
STEP Planned
WEST Operating

Fusion needs tritium, and the world's civilian stock comes mostly from CANDU fission reactors. See the fusion overview.

BEST in context

14 of the 24 fusion projects on record use the tokamak approach: 7 operating, 3 under construction, 3 planned and 1 closed.

It lists a target date of 2027, 1 year from now; of the 7 projects that list one, none lists an earlier year. A target date is the project's own aim, not a forecast.

Its stated fusion power target is 200 MW, 4th of the 6 projects that state one (median 300 MW).

MeasureBESTMedian of all projectsStanding
Target date202720281 of 7 (earliest first)
Fusion power target (MW)2003004 of 6

Worked out from the entries on this site only, so a figure compares BEST with what is recorded here, not with everything that exists. An entry with no value for a measure is left out of that measure's ranking and median.