Catawba nuclear power plant
Catawba nuclear power plant is a nuclear power station in United States with 2 operating units totalling 2,376 MW gross. The site has 2 units on record in total.
Units
| Unit | Status | Type | Model | Gross MW | Online |
|---|---|---|---|---|---|
| Unit 1 | PWR | WH 4LP (ICECND) | 1,188 | 1985 | |
| Unit 2 | PWR | WH 4LP (ICECND) | 1,188 | 1986 |
Unit by unit
Each unit's rating, type and milestone dates as recorded by the Global Nuclear Power Tracker, with any correction we made to it. A dash or "not disclosed" means the source does not give the value.
Catawba nuclear power plant 1
| Reactor type | Pressurised water reactor (PWR) |
|---|---|
| Model | Westinghouse 4-loop |
| Size class | Large |
| Gross capacity | 1,188MW |
| Net capacity | 1,160MW |
| Thermal output | 3,411MWt |
| Enrichment | 3–5% U-235 |
| NSSS vendor | Westinghouse Electric Company |
| Owner | North Carolina Electric Membership Corp100% |
| Operator | Duke Energy |
| Construction start | 1 May 1974 |
|---|---|
| First criticality | 7 Jan 1985 |
| Grid connection | 22 Jan 1985 |
| Commercial operation | 29 Jun 1985 |
Live status, outage record and fuel chain for Catawba nuclear power plant 1
Catawba nuclear power plant 2
| Reactor type | Pressurised water reactor (PWR) |
|---|---|
| Model | Westinghouse 4-loop |
| Size class | Large |
| Gross capacity | 1,188MW |
| Net capacity | 1,150MW |
| Thermal output | 3,411MWt |
| Enrichment | 3–5% U-235 |
| NSSS vendor | Westinghouse Electric Company |
| Owner | North Carolina Municipal Power Agency Number 1100% |
| Operator | Duke Energy |
| Construction start | 1 May 1974 |
|---|---|
| First criticality | 8 May 1986 |
| Grid connection | 18 May 1986 |
| Commercial operation | 19 Aug 1986 |
Live status, outage record and fuel chain for Catawba nuclear power plant 2
Fuel supply
Which fabricators are documented as able to make the fuel this plant's units take. This is capability from our supplier table, not a statement of who the operator buys from: utilities do not publish fuel contracts.
| Fuel | Units here | Documented fabricators | Enrichment |
|---|---|---|---|
| PWR (square-lattice) fuel | 2 | China National Nuclear Corporation, ENUSA Industrias Avanzadas, Framatome, KEPCO Nuclear Fuel, Mitsubishi Heavy Industries, Westinghouse Electric Company | Enriched |
United States runs 63 operating units on PWR (square-lattice) fuel. 6 fabricators are documented for it. Westinghouse Electric Company is based in United States.Country exposure
Catawba nuclear power plant in context
By gross operating capacity Catawba nuclear power plant is the 18th largest of 54 operating nuclear sites in the United States, holding 2% of the country's operating capacity, and ranks 70th of 172 worldwide.
Its operating units started up between 1985 and 1986; the median unit is 40.5 years old, younger than the median of 45.0 in the United States.
The 2 units with both construction and grid dates on record took 10.7 to 12.0 years (median 11.4) from construction start to grid connection; the median across all reactors connected in the 1980s is 7.3 years.
The nearest other tracked nuclear sites are McGuire nuclear power plant (44 km), Virgil C Summer nuclear power plant (87 km) and H. B. Robinson nuclear power plant (110 km).
2 operating units are rated differently now from their design net capacities: Unit 1 +1.3% and Unit 2 +0.4%.
Build time by unit
| Unit | Construction start | Grid connection | Years | Fleet median, same decade |
|---|---|---|---|---|
| Unit 1 | 1974 | 1985 | 10.7 | 7.3 (1980s) |
| Unit 2 | 1974 | 1986 | 12.0 | 7.3 (1980s) |
Nearest tracked nuclear sites
| Site | Country | Distance | Operating GW gross |
|---|---|---|---|
| McGuire nuclear power plant | United States | 44 km | 2.4 |
| Virgil C Summer nuclear power plant | United States | 87 km | 1.0 |
| H. B. Robinson nuclear power plant | United States | 110 km | 0.8 |
How these are worked out: ranks use gross operating capacity; ages count from the start-up year on record, as on the age page; build times run from construction start to grid connection, as on the build-times page; ratings are the tracker's net and design net capacity, as on the uprates page. Distances are straight-line between exact positions, so a site with only an approximate position gets none. A unit missing a date or a rating is left out of the figure that needs it.
Earthquakes nearby
Loading the latest USGS check…
| Time (UTC) | Mag | Depth | Epicentre | Distance |
|---|
Magnitude 4.0 and above within 200 km of Catawba nuclear power plant's listed coordinates, past 30 days. This is distance, not shaking: it says nothing about damage or any change in operation. Every plant.
| Location | South Carolina, United States |
|---|---|
| Coordinates | 35.0514, -81.0694 |
| Elevation | about 185 mabove sea level |
| Setting | About 250 km from the sea |
| Region | Northern America |
| Units by status | Operating: 2 |
Elevation is read at the listed coordinates from a 30 m terrain model (SRTM 30 m). Two independent models differ by a median of 6 m across our plants and by up to about 40 m on steep or coastal ground, and a point on a shoreline can read as sea level. Distance to the water is measured to a generalised 1:10 million coastline, so a few kilometres or less is not resolved. This is context, not a design-basis or flood-risk figure.
| Owners | North Carolina Electric Membership Corp North Carolina Municipal Power Agency Number 1 |
|---|---|
| Operators | Duke Energy |
Put this plant on your own page: embed a card, or compare it with another plant.
Sources
- Global Nuclear Power Tracker, Global Energy Monitor, August 2026 release , CC BY 4.0 · retrieved 2026-09-06
- GEM.wiki entry (further reading) , CC BY-SA 4.0, linked, not quoted
How these sources are used, including the corrections applied on top of them and what is deliberately left blank · download the underlying data