Neckarwestheim nuclear power plant 2
Neckarwestheim nuclear power plant 2 is a pressurised water reactor unit at Neckarwestheim nuclear power plant in Germany rated at 1,400 MW gross. It is retired. Commercial operation began 15 Apr 1989.
| Reactor type | Pressurised water reactor (PWR) |
|---|---|
| Model | Konvoi |
| Size | Largeabove 300 MWe |
| Coolant | Light water |
| Moderator | Light water |
| Gross capacity | 1,400MW |
| Net capacity (reference) | 1,310MW |
| Net capacity (design) | 1,225MW |
| Thermal output | 3,850MWt |
| NSSS vendor | not on record |
| Typical enrichment | 3–5% U-235 |
| Site | Neckarwestheim nuclear power plant |
|---|---|
| Unit | 2 |
| Country | Germany |
| Owner | EnBW Kernkraft GmbH100% |
| Operator | EnBW Kernkraft |
| Coordinates | 49.0408, 9.1759 |
- China National Nuclear Corporation PWR fuel assemblies
- ENUSA Industrias Avanzadas PWR and BWR fuel assemblies
- Framatome PWR fuel assemblies
- KEPCO Nuclear Fuel PWR fuel assemblies
- Mitsubishi Heavy Industries PWR fuel assemblies
- Westinghouse Electric Company PWR fuel assemblies
Enriched fuel means this unit sits downstream of five conversion plants and four enrichment operators holding 88% of world capacity between the top three.
Timeline
- 9 Nov 1982Construction start
- 29 Dec 1988First criticality
- 3 Jan 1989Grid connection
- 15 Apr 1989Commercial operation
- 15 Apr 2023Permanent shutdown
Other units at Neckarwestheim nuclear power plant
| Unit | Status | Gross MW |
|---|---|---|
| Neckarwestheim nuclear power plant 1 | Retired | 840 |
Other Konvoi units
3 units worldwide share this model designation.
| Unit | Country | Status | Gross MW |
|---|---|---|---|
| Emsland nuclear power plant | Germany | Retired | 1,406 |
| Isar nuclear power plant 2 | Germany | Retired | 1,485 |
Sources
- Global Nuclear Power Tracker, Global Energy Monitor, August 2026 release , CC BY 4.0 · retrieved 2026-09-06 · this unit last researched by GEM on 2024-05-14
- GEM.wiki entry (further reading) , CC BY-SA 4.0, linked, not quoted
How these sources are used, including the corrections applied on top of them and what is deliberately left blank · download the underlying data