Urenco is a GBR company active in the nuclear fuel chain as enricher, deconversion.

A tri-national enrichment consortium created by the 1970 Treaty of Almelo, owned one third each by the UK government, the Dutch government, and a joint venture of the German utilities E.ON and RWE. It pioneered the gas centrifuge over gaseous diffusion. Western enrichment costs collapsed. Four plants. Almelo, Gronau, Capenhurst and Eunice, New Mexico, give it roughly a quarter of world capacity and the only significant non-Russian, non-Chinese capacity outside France.

Company
HeadquartersStoke Poges, United Kingdom
Founded1971
Ownershipstate
Roles in the chainenricher, deconversion

Position in the chain

Downstream

Enriched uranium from this company feeds fuel fabrication, and from there 373 operating reactors across these types. Heavy water reactors are absent because they run on natural uranium and skip enrichment entirely.

Facilities

FacilityStageCountryCapacity / outputStatus
Urenco ChemPlants, Capenhurst deconversion GBR 10,000tU/yr operating
Urenco Almelo enrichment NLD 5,100tSWU/yr operating
Urenco USA, National Enrichment Facility enrichment USA 4,650tSWU/yr operating
Urenco Capenhurst enrichment GBR 4,500tSWU/yr operating
Urenco Gronau enrichment DEU 3,600tSWU/yr operating
Urenco Capenhurst HALEU line haleu GBR not disclosed planned

Urenco in context

In enrichment Urenco holds 17,300 of the 68,076 tSWU/yr of world enrichment capacity in 2025 (25%), ranking 2nd of the 4 named operators in the source.

Urenco has 6 facilities on record in 4 countries (United Kingdom, Netherlands, Germany and United States): 5 operating and 1 planned, licensing or under construction. The oldest operating one was commissioned in 1973.

Share of each stage it works in

StageCompanyWorld totalShareRankSource
Enrichment17,300tSWU/yr68,076(2025)25%2 of 4World Nuclear Association, Uranium Enrichment

How these are worked out: shares and ranks use the world totals cited in the table, and only named companies are ranked (unnamed or country-level entries in a source are not). A facility with no stated capacity is counted as a facility but adds nothing to a capacity figure. Vendor figures count operating units where this company is the recorded reactor vendor; ages count from the start-up year on record, and build times run from construction start to grid connection, as on the age and build-times pages.

Sources

How these sources are used, including the corrections applied on top of them and what is deliberately left blank · download the underlying data