Leningrad nuclear power plant
Leningrad nuclear power plant is a nuclear power station in Russia with 4 operating units totalling 4,376 MW gross. The site has 8 units on record in total.
Units
| Unit | Status | Type | Model | Gross MW | Online |
|---|---|---|---|---|---|
| Unit 1-3 | LWGR | RBMK-1000 | 1,000 | 1980 | |
| Unit 1-4 | LWGR | RBMK-1000 | 1,000 | 1981 | |
| Unit 2-1 | PWR | VVER V-491 | 1,188 | 2018 | |
| Unit 2-2 | PWR | VVER V-491 | 1,188 | 2021 | |
| Unit 2-3 | Under construction | PWR | VVER-1200/V-491 | 1,199 | 2030 |
| Unit 2-4 | Under construction | PWR | VVER-1200/V-491 | 1,199 | 2032 |
| Unit 1-1 | Retired | LWGR | RBMK-1000 | 1,000 | 1974 |
| Unit 1-2 | Retired | LWGR | RBMK-1000 | 1,000 | 1976 |
Unit by unit
Each unit's rating, type and milestone dates as recorded by the Global Nuclear Power Tracker, with any correction we made to it. A dash or "not disclosed" means the source does not give the value.
Leningrad nuclear power plant 1-3
| Reactor type | Light water graphite reactor (LWGR) |
|---|---|
| Model | RBMK-1000 |
| Size class | Large |
| Gross capacity | 1,000MW |
| Net capacity | 925MW |
| Thermal output | 3,200MWt |
| Enrichment | 2–2.6% U-235 |
| NSSS vendor | Rosatom |
| Owner | Rosatom100% |
| Operator | Rosenergoatom |
| Construction start | 1 Dec 1973 |
|---|---|
| First criticality | 17 Sep 1979 |
| Grid connection | 7 Dec 1979 |
| Commercial operation | 29 Jun 1980 |
Leningrad nuclear power plant 1-4
| Reactor type | Light water graphite reactor (LWGR) |
|---|---|
| Model | RBMK-1000 |
| Size class | Large |
| Gross capacity | 1,000MW |
| Net capacity | 925MW |
| Thermal output | 3,200MWt |
| Enrichment | 2–2.6% U-235 |
| NSSS vendor | Rosatom |
| Owner | Rosatom100% |
| Operator | Rosenergoatom |
| Construction start | 1 Feb 1975 |
|---|---|
| First criticality | 29 Dec 1980 |
| Grid connection | 9 Feb 1981 |
| Commercial operation | 29 Aug 1981 |
Leningrad nuclear power plant 2-1
| Reactor type | Pressurised water reactor (PWR) |
|---|---|
| Model | VVER-1200/V-491 |
| Size class | Large |
| Gross capacity | 1,188MW |
| Net capacity | 1,101MW |
| Thermal output | 3,200MWt |
| Enrichment | 3–5% U-235 |
| NSSS vendor | Rosatom |
| Owner | Rosatom100% |
| Operator | Rosenergoatom |
| Construction start | 25 Oct 2008 |
|---|---|
| First criticality | 6 Feb 2018 |
| Grid connection | 9 Mar 2018 |
| Commercial operation | 29 Oct 2018 |
Leningrad nuclear power plant 2-2
| Reactor type | Pressurised water reactor (PWR) |
|---|---|
| Model | VVER-1200/V-491 |
| Size class | Large |
| Gross capacity | 1,188MW |
| Net capacity | 1,101MW |
| Thermal output | 3,200MWt |
| Enrichment | 3–5% U-235 |
| NSSS vendor | Rosatom |
| Owner | Rosatom100% |
| Operator | Rosenergoatom |
| Construction start | 15 Apr 2010 |
|---|---|
| First criticality | 29 Aug 2020 |
| Grid connection | 22 Oct 2020 |
| Commercial operation | 18 Mar 2021 |
Leningrad nuclear power plant 2-3 Under construction
| Reactor type | Pressurised water reactor (PWR) |
|---|---|
| Model | VVER-1200/V-491 |
| Size class | Large |
| Gross capacity | 1,199MW |
| Net capacity | 1,150MW |
| Thermal output | 3,200MWt |
| Enrichment | 3–5% U-235 |
| NSSS vendor | Rosatom |
| Owner | Rosatom100% |
| Operator | Rosenergoatom |
| Construction start | 14 Mar 2024 |
|---|---|
| Commercial operation | 1 Jan 2030 |
Leningrad nuclear power plant 2-4 Under construction
| Reactor type | Pressurised water reactor (PWR) |
|---|---|
| Model | VVER-1200/V-491 |
| Size class | Large |
| Gross capacity | 1,199MW |
| Net capacity | 1,150MW |
| Thermal output | 3,200MWt |
| Enrichment | 3–5% U-235 |
| NSSS vendor | Rosatom |
| Owner | Rosatom100% |
| Operator | Rosenergoatom |
| Construction start | 20 Mar 2025 |
|---|---|
| Commercial operation | 1 Jan 2032 |
Leningrad nuclear power plant 1-1 Retired
| Reactor type | Light water graphite reactor (LWGR) |
|---|---|
| Model | RBMK-1000 |
| Size class | Large |
| Gross capacity | 1,000MW |
| Net capacity | 925MW |
| Thermal output | 3,200MWt |
| Enrichment | 2–2.6% U-235 |
| NSSS vendor | Rosatom |
| Owner | Rosatom100% |
| Operator | Rosenergoatom |
| Construction start | 1 Mar 1970 |
|---|---|
| First criticality | 12 Sep 1973 |
| Grid connection | 21 Dec 1973 |
| Commercial operation | 1 Nov 1974 |
| Permanent shutdown | 22 Dec 2018 |
Leningrad nuclear power plant 1-2 Retired
| Reactor type | Light water graphite reactor (LWGR) |
|---|---|
| Model | RBMK-1000 |
| Size class | Large |
| Gross capacity | 1,000MW |
| Net capacity | 925MW |
| Thermal output | 3,200MWt |
| Enrichment | 2–2.6% U-235 |
| NSSS vendor | Rosatom |
| Owner | Rosatom100% |
| Operator | Rosenergoatom |
| Construction start | 1 Jun 1970 |
|---|---|
| First criticality | 6 May 1975 |
| Grid connection | 11 Jul 1975 |
| Commercial operation | 11 Feb 1976 |
| Permanent shutdown | 10 Nov 2020 |
Fuel supply
Which fabricators are documented as able to make the fuel this plant's units take. This is capability from our supplier table, not a statement of who the operator buys from: utilities do not publish fuel contracts.
| Fuel | Units here | Documented fabricators | Enrichment |
|---|---|---|---|
| RBMK fuel | 2 | TVEL Fuel Company | Enriched |
| VVER (hexagonal) fuel | 4 | TVEL Fuel Company, Westinghouse Electric Company | Enriched |
Russia runs 7 operating units on RBMK fuel. 1 fabricator is documented for it. TVEL Fuel Company is based in Russia. Every documented supplier is in Russia.Country exposure
Russia runs 23 operating units on VVER (hexagonal) fuel. 2 fabricators are documented for it. TVEL Fuel Company is based in Russia.Country exposure
Leningrad nuclear power plant in context
By gross operating capacity Leningrad nuclear power plant is the 1st largest of 10 operating nuclear sites in Russia, holding 15% of the country's operating capacity, and ranks 17th of 172 worldwide.
Its operating units started up between 1980 and 2021; the median unit is 26.5 years old, younger than the median of 37.5 in Russia.
The 6 units with both construction and grid dates on record took 3.8 to 10.5 years (median 6.0) from construction start to grid connection; the median across all reactors connected in the 1980s is 7.3 years.
The nearest other tracked nuclear sites are Loviisa nuclear power plant (160 km).
2 operating units are rated differently now from their design net capacities: Unit 2-1 +3.3% and Unit 2-2 +3.3%.
Build time by unit
| Unit | Construction start | Grid connection | Years | Fleet median, same decade |
|---|---|---|---|---|
| Unit 1-1 | 1970 | 1973 | 3.8 | 5.4 (1970s) |
| Unit 1-2 | 1970 | 1975 | 5.1 | 5.4 (1970s) |
| Unit 1-3 | 1973 | 1979 | 6.0 | 5.4 (1970s) |
| Unit 1-4 | 1975 | 1981 | 6.0 | 7.3 (1980s) |
| Unit 2-1 | 2008 | 2018 | 9.4 | 5.9 (2010s) |
| Unit 2-2 | 2010 | 2020 | 10.5 | 7.7 (2020s) |
Nearest tracked nuclear sites
| Site | Country | Distance | Operating GW gross |
|---|---|---|---|
| Loviisa nuclear power plant | Finland | 160 km | 1.1 |
How these are worked out: ranks use gross operating capacity; ages count from the start-up year on record, as on the age page; build times run from construction start to grid connection, as on the build-times page; ratings are the tracker's net and design net capacity, as on the uprates page. Distances are straight-line between exact positions, so a site with only an approximate position gets none. A unit missing a date or a rating is left out of the figure that needs it.
Earthquakes nearby
Loading the latest USGS check…
| Time (UTC) | Mag | Depth | Epicentre | Distance |
|---|
Magnitude 4.0 and above within 200 km of Leningrad nuclear power plant's listed coordinates, past 30 days. This is distance, not shaking: it says nothing about damage or any change in operation. Every plant.
| Location | Leningrad, Russia |
|---|---|
| Coordinates | 59.8525, 29.0486 |
| Elevation | about 55 mabove sea level |
| Setting | On the sea coast, 2.2 km from the water |
| Region | Eastern Europe |
| Units by status | Operating: 4 Under construction: 2 Retired: 2 |
Elevation is read at the listed coordinates from a 30 m terrain model (ASTER GDEM 30 m). Two independent models differ by a median of 6 m across our plants and by up to about 40 m on steep or coastal ground, and a point on a shoreline can read as sea level. Distance to the water is measured to a generalised 1:10 million coastline, so a few kilometres or less is not resolved. This is context, not a design-basis or flood-risk figure.
| Owners | Rosatom |
|---|---|
| Operators | Rosenergoatom |
Put this plant on your own page: embed a card, or compare it with another plant.
Sources
- Global Nuclear Power Tracker, Global Energy Monitor, August 2026 release , CC BY 4.0 · retrieved 2026-09-06
- GEM.wiki entry (further reading) , CC BY-SA 4.0, linked, not quoted
How these sources are used, including the corrections applied on top of them and what is deliberately left blank · download the underlying data