Nyongbyon nuclear power plant 3
Nyongbyon nuclear power plant 3 is a light water graphite reactor unit at Nyongbyon nuclear power plant in North Korea rated at 30 MW gross. It is mothballed. Commercial operation began 1 Jan 2023.
| Reactor type | Light water graphite reactor (LWGR) |
|---|---|
| Model | not disclosed |
| Size | Small300 MWe or less |
| Coolant | Light water |
| Moderator | Graphite |
| Gross capacity | 30MW |
| Net capacity (reference) | not disclosed |
| Net capacity (design) | not disclosed |
| Thermal output | 100MWt |
| NSSS vendor | not on record |
| Typical enrichment | 2–2.6% U-235 |
| Site | Nyongbyon nuclear power plant |
|---|---|
| Unit | 3 |
| Country | North Korea |
| Coordinates | 39.7959, 125.7551 |
Enriched fuel means this unit sits downstream of five conversion plants and four enrichment operators holding 88% of world capacity between the top three.
Timeline
- 1 Jan 2009Construction start
- 1 Jan 2023Commercial operation
Other units at Nyongbyon nuclear power plant
| Unit | Status | Gross MW |
|---|---|---|
| Nyongbyon nuclear power plant 1 | 5 | |
| Nyongbyon nuclear power plant 2 | Cancelled | 50 |
Sources
- Global Nuclear Power Tracker, Global Energy Monitor, August 2026 release , CC BY 4.0 · retrieved 2026-09-06 · this unit last researched by GEM on 2026-06-15
- GEM.wiki entry (further reading) , CC BY-SA 4.0, linked, not quoted
How these sources are used, including the corrections applied on top of them and what is deliberately left blank · download the underlying data