Linglong nuclear power plant 1

Under construction China Small
Gross capacity
125MW

Linglong nuclear power plant 1 is a pressurised water reactor unit at Linglong nuclear power plant in China rated at 125 MW gross. It is under construction. Commercial operation began 1 Jan 2026.

Specification
Reactor type Pressurised water reactor (PWR)
ModelACP-100
SizeSmall300 MWe or less
CoolantLight water
ModeratorLight water
Gross capacity125MW
Net capacity (reference)100MW
Net capacity (design)100MW
Thermal output385MWt
NSSS vendorChina National Nuclear Corporationall vendors
Typical enrichment3–5% U-235
Ownership & location
SiteLinglong nuclear power plant
Unit1
CountryChina
OwnerChina National Nuclear Power Co Ltd100%
OperatorCNNC Hainan Nuclear Power
Coordinates 19.4591, 108.8963
Fuel chain for this unit
Fuel form
Uranium dioxide pellets in zirconium-alloy cladding
Enrichment
3–5% U-235
Who makes this assembly
Upstream

Enriched fuel means this unit sits downstream of five conversion plants and four enrichment operators holding 88% of world capacity between the top three.

Fabricator capability is recorded against reactor type and model line, not against named units, utilities do not publish fuel contracts. See the fuel chain.

Timeline

  1. 13 Jul 2021Construction start
  2. 1 Jan 2026Commercial operation

Other ACP-100 units

7 units worldwide share this model designation.

UnitCountryStatusGross MW
Makran Coast nuclear power plant 1 Iran Cancelled 100
Makran Coast nuclear power plant 2 Iran Cancelled 100
Ningdu nuclear power plant 1 China Cancelled 125
Ningdu nuclear power plant 2 China Cancelled 125
Putian nuclear power plant 1-1 China Cancelled 100
Putian nuclear power plant 1-2 China Cancelled 100

Sources