Calder Hall nuclear power plant
Calder Hall nuclear power plant is a nuclear site in United Kingdom with 4 units on record. None is currently operating.
Units
| Unit | Status | Type | Model | Gross MW | Online |
|---|---|---|---|---|---|
| Unit 1 | Retired | GCR | MAGNOX | 60 | 1956 |
| Unit 2 | Retired | GCR | MAGNOX | 60 | 1957 |
| Unit 3 | Retired | GCR | MAGNOX | 60 | 1958 |
| Unit 4 | Retired | GCR | MAGNOX | 60 | 1959 |
Calder Hall nuclear power plant in context
The 4 units with both construction and grid dates on record took 2.6 to 3.7 years (median 3.3) from construction start to grid connection; the median across all reactors connected in the 1950s is 3.5 years.
The nearest other tracked nuclear sites are Heysham nuclear power plant (57 km), Hartlepool nuclear power plant (151 km) and Torness nuclear power plant (186 km).
Build time by unit
| Unit | Construction start | Grid connection | Years | Fleet median, same decade |
|---|---|---|---|---|
| Unit 1 | 1953 | 1956 | 3.1 | 3.5 (1950s) |
| Unit 2 | 1953 | 1957 | 3.5 | 3.5 (1950s) |
| Unit 3 | 1955 | 1958 | 2.6 | 3.5 (1950s) |
| Unit 4 | 1955 | 1959 | 3.7 | 3.5 (1950s) |
Nearest tracked nuclear sites
| Site | Country | Distance | Operating GW gross |
|---|---|---|---|
| Heysham nuclear power plant | United Kingdom | 57 km | 2.6 |
| Hartlepool nuclear power plant | United Kingdom | 151 km | 1.3 |
| Torness nuclear power plant | United Kingdom | 186 km | 1.4 |
How these are worked out: ranks use gross operating capacity; ages count from the start-up year on record, as on the age page; build times run from construction start to grid connection, as on the build-times page; ratings are the tracker's net and design net capacity, as on the uprates page. Distances are straight-line between exact positions, so a site with only an approximate position gets none. A unit missing a date or a rating is left out of the figure that needs it.
| Location | Borough of Copeland, England, United Kingdom |
|---|---|
| Coordinates | 54.4184, -3.4921 |
| Elevation | about 30 mabove sea level |
| Setting | On the sea coast, 1.1 km from the water |
| Region | Northern Europe |
| Units by status | Retired: 4 |
Elevation is read at the listed coordinates from a 30 m terrain model (SRTM 30 m). Two independent models differ by a median of 6 m across our plants and by up to about 40 m on steep or coastal ground, and a point on a shoreline can read as sea level. Distance to the water is measured to a generalised 1:10 million coastline, so a few kilometres or less is not resolved. This is context, not a design-basis or flood-risk figure.
| Owners | Nuclear Decommissioning Authority (United Kingdom) |
|---|---|
| Operators | Sellafield |
Put this plant on your own page: embed a card, or compare it with another plant.
Sources
- Global Nuclear Power Tracker, Global Energy Monitor, August 2026 release , CC BY 4.0 · retrieved 2026-09-06
- GEM.wiki entry (further reading) , CC BY-SA 4.0, linked, not quoted
How these sources are used, including the corrections applied on top of them and what is deliberately left blank · download the underlying data