Skip to content

Mitsubishi 4-loop

The Mitsubishi 4-loop is a Generation II pressurised water reactor from Mitsubishi Heavy Industries. 4 units are operating and 0 are under construction, out of 5 on record.

Operating
4
4.7 GW gross
Under construction
0
Planned
0
Cancelled
0
0 retired

Mitsubishi's largest PWR, at Ohi 3 and 4 and Genkai 3 and 4. It is the immediate technical ancestor of the APWR, which Mitsubishi offered in the United States and Japan and never built. Mitsubishi is now the principal supplier to the Japanese restart programme rather than a builder of new plants.

Design
VendorMitsubishi Heavy Industries
Reactor typePressurised water reactor (PWR)
GenerationII
Capacity range1150–1250 MWe gross
Also recorded asM (4-loop)in the source tracker
CoolantLight water
Typical enrichment3–5% U-235
Where it is built
Japan 5 units, 4 operating

How long it took to build

Years from construction start to grid connection, for units with both dates on record. The median across 4 finished units is 4.2 years.

UnitCountryStartedConnectedYears
Ohi nuclear power plant 3Japan 19871991 3.7
Ohi nuclear power plant 4Japan 19881992 4.0
Genkai nuclear power plant 3Japan 19881993 5.0
Genkai nuclear power plant 4Japan 19921996 4.3

All Mitsubishi 4-loop units

UnitCountryStatusGross MWOnline
Genkai nuclear power plant 3 Japan Operating 1,180 1994
Genkai nuclear power plant 4 Japan Operating 1,180 1997
Ohi nuclear power plant 3 Japan Operating 1,180 1991
Ohi nuclear power plant 4 Japan Operating 1,180 1993
Tsuruga nuclear power plant 2 Japan Mothballed 1,160 1987

Sources

How these sources are used, including the corrections applied on top of them and what is deliberately left blank · download the underlying data

Try